Bill Heard Chevrolet Entry Facade
Bill Heard Chevrolet Entry Facade
BILL HEARD CHEVROLET ENTRY FAÇADE
8-23-07 to 10-2-07
Contract Amount = $377k
This is a small project I did in between the Scottsdale Senior Center and the Red Rock Ranger Station. Not much self performed work here except the usual concrete work. We pulled off the job at the completion of the structure as there was a long lead time on the exterior sheathing to match the existing structure. Another Superintendent finished the project when the sheathing came in as I was responsible for the building layout and footing/stem wall construction on the Red Rock Ranger Station at that time.